Current Status
Waiting on shipping.
|
-
Performance
-
Time
-
Financial
<
>
Currently no end objectives have been met.
Balloon/C&C is currently testing sensor, code, and creating the flight termination mechanism.
Recovery is currently creating a vehicle prototype. The videos below show the fin tests, it is connected to a test platform.
Ground station is currently testing flight tracking and creating code.
|
|
What we are working on now:
Ordering hardware.
Testing parts and design.
Manufacturing recovery vehicle prototype.
Next milestone: Start of fabrication and manufacturing on Jan 7
We are currently on track to finish on time unless there is a significant delay in shipping.
Ordering hardware.
Testing parts and design.
Manufacturing recovery vehicle prototype.
Next milestone: Start of fabrication and manufacturing on Jan 7
We are currently on track to finish on time unless there is a significant delay in shipping.
Current Funding: $2000
Funds Required: $2370
Deficit: $370
Funds Required: $2370
Deficit: $370